Table 1 Activity costs of project

From: A genetic algorithm-based optimizing approach for project time-cost trade-off with uncertain measure

Activity

Normal cost

Additional cost

(i,j)

c ij

d ij

(1,2)

170

200

(1,3)

300

280

(1,4)

65

70

(2,5)

270

300

(3,5)

135

150

(3,6)

75

90

(3,7)

150

100

(4,7)

600

400

(5,8)

85

100

(6,8)

300

400

(6,9)

95

90

(6,10)

130

140

(7,10)

200

240

(8,11)

90

120

(9,11)

200

180

(10,11)

320

380