From: A genetic algorithm-based optimizing approach for project time-cost trade-off with uncertain measure
Activity | Normal cost | Additional cost |
---|---|---|
(i,j) | c ij | d ij |
(1,2) | 170 | 200 |
(1,3) | 300 | 280 |
(1,4) | 65 | 70 |
(2,5) | 270 | 300 |
(3,5) | 135 | 150 |
(3,6) | 75 | 90 |
(3,7) | 150 | 100 |
(4,7) | 600 | 400 |
(5,8) | 85 | 100 |
(6,8) | 300 | 400 |
(6,9) | 95 | 90 |
(6,10) | 130 | 140 |
(7,10) | 200 | 240 |
(8,11) | 90 | 120 |
(9,11) | 200 | 180 |
(10,11) | 320 | 380 |