Table 3 The quasi-optimal solutions for expected value model

From: Uncertain Resource-Constrained Project Scheduling Problem with Net Present Value Criterion

Generation and popsize Quasi-optimal schedule E[NPV] E[makespan]
150 and 30 1,3,19,4,2,9,5,14,6,20,13,8,10,22,27,23,18, 3172 65
  12,11,17,15,16,7,21,24,29,26,28,31,25,30,32   
500 and 30 1,4,3,19,16,2,5,9,8,13,14,27,23,6,12,11,22,7, 3182.4 65.068
  18,10,15,26,24,20,25,17,30,21,28,31,29,32   
500 and 30 1,2,8,3,4,6,12,9,19,13,15,22,11,27,16,5,14,23, 3144.7 71.263
  17,7,26,20,21,28,18,31,24,10,29,25,30,32   
500 and 30 1,3,4,19,2,9,23,6,5,14,13,10,20,8,16,22,7,11, 3147.3 69.505
  27,12,18,17,24,15,21,29,26,25,28,30,31,32   
150 and 50 1,4,2,16,8,3,6,22,13,7,19,17,23,12,5,11,26,10, 3148.4 63.763
  9,14,20,27,24,25,15,21,28,31,18,30,29,32   
150 and 50 1,2,4,8,3,6,7,22,11,12,19,5,13,23,16,26,17,9, 3180.2 60.505
  24,10,14,20,18,25,15,29,21,28,27,31,30,32   
150 and 50 1,3,2,9,27,14,5,4,19,8,13,23,20,16,6,10,22,12, 3151.5 68.753
  17,11,7,26,21,28,15,24,18,25,31,30,29,32   
150 and 50 1,2,4,16,8,3,6,11,12,5,9,19,13,24,17,7,27,25, 3156.8 62.131
  14,10,20,22,18,15,23,26,21,29,30,28,31,32   
150 and 50 1,2,4,8,3,6,11,12,9,19,5,10,15,23,24,22,27,14, 3232 68.258
  20,7,13,26,16,17,25,21,28,30,18,29,31,32   
150 and 50 1,2,4,8,3,6,12,11,13,19,16,7,22,24,5,18,9,25, 3162.6 73.288
  14,15,29,27,17,23,20,10,21,30,26,28,31,32