Table 5 The quasi-optimal solutions for chance maximization model

From: Uncertain Resource-Constrained Project Scheduling Problem with Net Present Value Criterion

\(\overline {Npv}\)

Quasi-optimal schedule

Uncertainty

NPV

3000

1,4,2,16,8,3,6,22,13,9,19,11,5,7,27,23,14,17,

0.99

3021.7

 

10,12,20,15,18,26,24,25,29,21,28,31,30,32

  

3100

1,2,4,8,3,6,12,22,5,19,9,11,10,23,14,18,24,26,

0.69

3104.6

 

13,16,20,7,15,17,21,28,25,27,30,31,29,32

  

3200

1,4,2,8,6,3,11,12,5,16,22,9,19,14,23,24,18,15,

0.46

3203.7

 

25,27,26,7,13,17,20,21,29,10,28,31,30,32

  

3300

1,3,4,19,6,9,5,2,14,20,13,22,27,23,10,8,12,11,

0.27

3301.6

 

18,26,7,16,24,15,17,25,21,30,28,31,29,32

  

3400

1,2,4,16,8,3,6,11,12,19,5,15,9,10,24,23,14,18,

0.07

3403.8

 

13,22,29,7,25,20,17,21,26,27,28,31,30,32